job_queue_processes parameter=100
The 11 oracle jobs run every second to check the next_run_date of a report specified in a table to see if it is time to call the work_summary package to run that report (which summaries data in one table and inserts the result into another).
After the work_summary package completes running the report, it updates the last_run_time and next_run_time fields in that table for that report.
The last_run_date of the reports in that table is the 18th. So I know the reports are not being run by the jobs.
I can the reports using that package manually which is fine but even then the last_run_time and next_run_time fields are not updated!